Letter from Coastal Asphalt on Roadbed Work Scheduled for next week.

Below is an update from Coastal Asphalt on the Roadbed Work scheduled for next week.  I have highlighted the important points to follow.

From Coastal Asphalt

The work is tentatively scheduled to begin the week OF March 20th and will consist of
cleaning the asphalt and applying two coats of asphalt sealer. Once the application is
completed, it is necessary to stay off the roadway until traffic control devices have
been removed (typically 24 hours). The process calls for us to divide Huntington Lakes
Villas into sections. Please refer to the enclosed color coded map identifying the scheduled
days we plan on doing each section.

Coastal Asphalt, LLC will strive to make this process as minimally disruptive to your
everyday lives as possible. Coastal Asphalt, LLC will work with the mail carriers and other
delivery personnel and will assist you in knowing where to park and how to come and go
to your respective homes. Please have your cars moved by 7:00AM on the morning
your section will be sealed. Please ensure your irrigation is turned off the night before
your scheduled date and remains off for 24 hours after seal coating is complete. IF IT
RAINS ON THE DAY YOU’RE SCHEDULED YOUR PHASE WILL BE MOVED TO THE
END.

 

Huntington Lakes Villas – Homeowners Letter

 

Huntington Lakes Phase Map

 

You will receive a final notification next Tuesday, 3/21 in your mailbox as a reminder and notification if weather changes the schedule.

0 replies

Leave a Reply

Want to join the discussion?
Feel free to contribute!

Leave a Reply

Your email address will not be published. Required fields are marked *